Set Material Due Date and Auto-Pick Offers Based on Lead Time in Cableteque
This explains how to configure a quote in Cableteque so only offers that can arrive by the required material due date are shown. It helps ensure selected suppliers meet the project timeline before auto-picking the best offers.
Key Steps
1. Enable the Material Due Date filter for sourcing 0:01
In Cableteque, open the sourcing options for the quote.
Turn on the setting for material due date.
This filter limits results to offers whose factory lead time can meet the batch material due date.
2. Save the sourcing settings 0:11
After enabling the material due date option, click Save.
Confirm the setting is applied before moving to the quote details.
This ensures future offer selection uses the due-date constraint.
3. Set the quote’s material due date 0:25
In the top-left area of the quote, locate the quote name and related settings.
Open the material due date field.
Enter the required date by which materials must arrive.
Example: set the due date to the end of August if all materials are needed by then.
4. Save the due date and auto-pick best offers 0:31
Save the quote after entering the material due date.
Run Auto-Pick All Best Offers.
Cableteque will now only display offers that can arrive before the selected due date.
5. Review the filtered offer results 0:43
Review the offers returned by the system after auto-picking.
Confirm that in-stock items and eligible lead times are being selected.
Check any out-of-stock items carefully to ensure the system is still meeting the due-date requirement.
6. Verify the selected supplier meets the lead-time requirement 0:53
Inspect the chosen offer for each part.
Confirm the selected supplier has the shortest lead time that still meets the due date.
Example: Highland was selected because its 33-day lead time allowed the part to arrive in time.
7. Confirm non-selected offers were excluded for timing reasons 1:01
Review why other suppliers were not chosen.
If an offer was excluded, verify it would have arrived after the material due date.
Use this check to validate that the filter is working correctly and protecting the project schedule.
Cautionary Notes
Do not assume the lowest-cost offer will be selected if it cannot meet the material due date.
Make sure the material due date is saved before running Auto-Pick All Best Offers.
If the due date is entered incorrectly, the system may filter out valid offers or select unsuitable ones.
Always verify the selected supplier’s lead time against the required date before finalizing the quote.
Tips for Efficiency
Set the material due date as early as possible in the quoting process to avoid rework.
Use the due-date filter before reviewing offers to reduce manual sorting.
After auto-picking, quickly scan for out-of-stock items and long lead times to confirm the results are aligned with the schedule.
Keep the quote’s required date updated whenever project timelines change.