Choosing RFQ in Materials

P
Written by Prarthana Gupta

Importing and Completing RFQs to Populate the Materials Phase

Objective

This explains how to import an RFQ response, manually adjust quote details if needed, and mark the RFQ as complete so it appears in the materials phase. It also covers how to locate the completed RFQ and select the corresponding offer.

Key Steps

1. Import the RFQ response file 0:00

generated-image-at-00:00:00

  • In the RFQ area, select Import RFQ.

  • Use this option when you receive a response from a customer or supplier.

  • Drag and drop the returned Excel file or PDF into the import window.

  • Allow the system to automatically update the RFQ details from the uploaded file.

2. Manually edit RFQ quote details if needed 0:24

generated-image-at-00:00:24

  • If the RFQ response needs correction or adjustment, open the RFQ record.

  • Click the Edit button.

  • Go to the Actions tab.

  • Update the quote values to match what was actually provided.

  • Remove any quote quantities that were not included in the response.

  • Save the changes when finished.

3. Confirm the RFQ is marked complete 1:03

generated-image-at-00:01:03

  • After saving the updated quote information, verify that the RFQ is marked as complete.

  • Return to the Materials section.

  • Search for the relevant part number.

  • Look for the RFQ indicator icon showing that the RFQ has been completed.

4. Locate the completed RFQ in the offer queue 1:16

generated-image-at-00:01:16

  • Open the part record and select Explore All Offers.

  • Find the completed RFQ in the offer queue.

  • Review the available offer source, such as the supplier name shown in the queue.

  • Select the correct offer to continue.

5. Pull the selected offer into the workflow 1:30

generated-image-at-00:01:30

  • After selecting the offer, confirm that the system pulls in the requested quote.

  • Verify the offer details match the RFQ response you imported or edited.

  • Proceed with the materials phase using the completed RFQ offer.

Cautionary Notes

  • Ensure the imported file is the correct RFQ response before uploading.

  • If editing manually, double-check quantities and pricing so the RFQ reflects the supplier’s actual response.

  • Do not save until all quote details are verified, as saving will mark the RFQ complete.

  • Confirm you are working on the correct part number before selecting an offer.

Tips for Efficiency

  • Use the import feature whenever possible to reduce manual data entry.

  • If the supplier response is in PDF or Excel format, upload it directly instead of retyping values.

  • Review the RFQ response immediately after import to catch missing or incorrect quote values early.

  • Use the part number search in Materials to quickly confirm completion and locate the RFQ.